10/11 Renewal of a MAN 8L32-40 main engine’s crankshaft
05/12 Full re-tubing of main and auxiliary boilers
09/13 Rudder Carrier renewal
11/13 Cargo crane gear box renewal
02/14 Chemical carrier catwalk partial renewal
05/14 Overhauling of a Pielstick 8PC2-6L Main engine
08/14 Overhauling of two Daihatsu 6DK-20 diesel generators
06/14 Complete re-tubing of a composite boiler
02/15 Renewal of an MAN B&W 6L23/30 diesel generator crankshaft
06/15 Conversion and fitting of an AVR for a Cruise vessel
03/16 Renewal of a MAN 8L32-40 main engine’s crankshaft
06/16 Re-activation of two laid-up chemical carriers
11/16 Cruise vessel dry docking attendance
02/17 Full main engine overhauling and renewal of the vessel’s key components along with its re-classification
04/17 Sound proofing of a cruise vessel’s room located above the engine room
06/17 MAN 6S60MC M/E overhauling
09/17 Attendance and co-ordination of various projects for a cruise vessel during its D/D
09/17 Complete renewal of an American owned cruise vessel’s Sail System
02/18 Complete renewal of an American owned cruise vessel’s Sail System
11/18 Renewal of a cruise vessel’s sail’s monitoring system and the cabling lay-out
04/19 Complete overhaul of four Wartsila 50DF MGE’s on board an LNG carrier
10/19 Overhaul of one W12V50DF and a 6L50DF MGE’s on board an LNG carrier
11/19 Overhaul of two Wartsila W12V50DF MGE’s on board an LNG Carrier
12/19 Overhaul of one MAN 9L51/60DF on board an LNG Carrier
02/20 Overhaul of two MAN 8L51/60DF on board an LNG Carrier
03/20 Overhauling of a MAN 9L51/60DF on board an LNG Carrier
03/20 Overhauling of two MAN 60G50ME-C9.5 engines on board two separate LPG vessels
07/20 Overhauling of a Wartsila 6L50DF and one Wartsila W12V50DF MGE’s on board an LNG Carrier
10/20 Overhauling of a Wartsila 6L50DF MGE equipped on an LNG Carrier
12/20 Re-winding of two Bow-Thruster auto-transformers in the workshop and their installation/start-up on board.
01/21 Overhauling of two Wartsila 12V50DF MGEs equipped on an LNG Carrier
And MORE…